Basketball wooden floor is warm in winter and cool in summer, which is a relatively advanced indoor floor. It is necessary to carefully follow each step during installation to make our wooden floor long-lasting and relatively simple to maintain. Many customers are more entangled and cautious after purchasing our wood flooring materials, and will ask some questions many times in terms of installation. Next, I will tell you about the installation process.

1. After hiring a professional installation team to arrive, it is necessary to clean up and shovel cement slurry or some water-based substances on the entire basketball court floor that needs to be installed. Only in this way can the foundation be completely cleaned and it is not easy to get water out, otherwise it will be very difficult to get water out of the ground.
2. Next, you need to find the reference point on the ground through the instrument, in order to be parallel and flat according to the installation line when installing the wooden keel. Generally, use a level measuring instrument to rise to a distance of about 3m, and start installing the keel after ensuring the level.
3. Install the lower keel first. It takes a lot of time to keep the keels of the entire site symmetrical and neat according to the spacing of 4cm, and the general foundation is especially critical. The distance between the upper and lower keels is 4cm. Insert the keel crosswise, and install rubber pads where the entire keel intersects, this is to protect the load-bearing before the upper keel and the lower keel, and will not wear the surface of the keel. After the whole is fixed, it is necessary to spray anti-corrosion paint on the edge of the keel, and finally it is necessary to observe whether the entire keel reaches the same level.
4. Next, it is necessary to lay plywood on the upper layer of the keel. This layer of plywood is a very durable and environmentally friendly material. Fixing it to the keel will add a layer of protection.
5. Then add the critical moisture-proof film. Each roll of moisture-proof film is glued together with glue to form a protective effect on the floor material.
6. Then we go to the installation of the wooden floor on the top floor. The whole installation is laid relatively perpendicular to the upper keel. The wooden floor needs to be checked for burrs and cracks, which generally do not meet the configuration requirements. Then When fixing the wooden floor, it is not necessary to be too tight, which will cause damage to the wooden floor and the foundation.
7. The last thing is to check and test the installation of the entire wooden floor. The professional team will measure whether it meets professional standards, then clean the entire surface, and then use environmentally friendly paint to draw lines, so that a complete wooden floor basketball court is installed.