Primer layer 1,scraping 2,cured time will take 48 hours ( 30 ℃ ) 3,continute to process next layer when it dried. TIP : construction in rainy days was prohibited."
Buffer coating layer scraping 1 layer. curd time will take 48 hours ( 30℃ ). TIP : construction in rainy days was prohibited."
Wear coating layer scraping 1 layer. curd time will take 48 hours ( 30℃ ). TIP : construction in rainy days was prohibited.
Spray coating Spray 2 layers Curing time will take about 24 hrs for per layer ( 30℃ ) . TIP : construction in rainy days was prohibited.
PU Line Marking Roller paint 2 layers Dry time will take about 8 hours for each layer ( 30℃ ). TIP : construction in rainy days was prohibited.