Primer layer 1. Scrape and apply 2. Each layer needs 48 hours of curing time (30℃) 3. After drying, continue to apply the next layer
Buffer coating Spray 1 layer in the same way, and the drying time must be at least 72 hours (30℃).
Sealing layer 2.30kg/sq.m G06 (1.8kg) + fine glue (0.5kg) Paint Scrape and apply 1 layer Please note: Apply this layer and the next layer on the same line. Separate several areas to complete the installation of this layer
Broadcast EPDM Curing time requires 8 - 10 hours (30℃ as a reference) Reminder: Separate several areas to complete the installation of this layer
PU marking 2 components Spray 2 layers with roller paint in the same way as the left photo. The drying time for each layer is about 3 hours (30'℃,).