Sandwich Layer Running Track details

Thickness:9-15mm (recommend 13mm)
Material:EPDM granules + PU Binder
Base:Cement or Asphalt
Color:red,blue and customized
Usage:school, stadium, national training center
Service Life:10 years
Installation

Sandwich Layer Running Track Installation Method

Primer layer
1. Scrape and apply
2. Each layer needs 48 hours of curing time (30℃)
3. After drying, continue to apply the next layer

Buffer coating
Spray 1 layer in the same way, and the drying time must be at least 72 hours (30℃).

Sealing layer
2.30kg/sq.m G06 (1.8kg) + fine glue (0.5kg)
Paint
Scrape and apply 1 layer
Please note: Apply this layer and the next layer on the same line.
Separate several areas to complete the installation of this layer

Broadcast EPDM
Curing time requires 8 - 10 hours (30℃ as a reference)
Reminder: Separate several areas to complete the installation of this layer

PU marking
2 components
Spray 2 layers with roller paint in the same way as the left photo.
The drying time for each layer is about 3 hours (30'℃,).